Short answer · 11 min read
Key takeaways
- Both devices meet the same goal: the generator and the utility can never feed your panel at the same time.
- An interlock must be made and listed for your exact panel; many older or obsolete panels have none.
- A manual transfer switch limits you to the circuits wired into it, often 6 to 10.
- The generator breaker is backfed, so the NEC requires it to be held in with a retaining fastener.
- Standby generators use an automatic transfer switch instead; portables use an interlock or manual switch.
Short answer: if your panel has a listed interlock kit and you are comfortable flipping breakers, an interlock gives you the whole panel for less. If your panel has no kit, you want only a handful of circuits, or someone less confident will be switching over, a manual transfer switch is the cleaner choice. Either way, the job includes an inlet, a cord and a permit when one is required.
What does a generator interlock kit do?
The generator breaker is a two-pole breaker, typically 30 or 50 amps, installed in the top spaces of your panel next to the main. A cable runs from it to the power inlet box outside. Because generator power enters the panel through that breaker, it is called a backfed breaker, and the NEC (Section 408.36(D)) requires a backfed breaker of this kind to be secured with an additional fastener so it cannot be pulled loose while energized.
How is a manual transfer switch different?
Common residential units handle 6 to 10 circuits, and a 240-volt load such as a well pump uses two positions. Before installation you choose the circuits: well pump, sump, furnace, fridge, a kitchen outlet circuit, some lighting. Those are the only circuits the generator can ever feed unless the switch is rewired later.
An automatic transfer switch (ATS) is a different device used with standby generators. It senses the outage, signals the generator to start and moves the load by itself. Portable generators do not use an ATS. Our post on portable vs standby generators explains where an ATS fits.
Interlock kit vs transfer switch: which is better?
Generator interlock kit vs manual transfer switch vs automatic transfer switch
| Feature | Interlock kit | Manual transfer switch | Automatic transfer switch |
|---|---|---|---|
| Used with | Portable generator | Portable generator | Standby generator |
| Circuits available | Any circuit in the panel | Only the prewired ones, often 6 to 10 | Whole house or selected loads |
| Switching | Main off, generator breaker on | Flip each circuit switch | Automatic |
| Panel fit | Needs a kit listed for your panel | Works beside most panels | Sized to the service |
| Load visibility | None unless added | Often built-in wattmeters | Load management on many models |
| Relative cost | Usually lowest | Moderate | Highest, part of a standby project |
| Easy for anyone in the house? | Needs care with breakers | Simpler, fewer choices | Nothing to do |
A rule of thumb
If you can name every circuit you want on generator power and there are eight or fewer, a manual transfer switch is a tidy answer. If you want to move power around the house as the outage goes on, an interlock suits you better.
Planning backup power or an EV charger?
What does the electrical code require for generator transfer equipment?
For an interlock, “listed” matters. Panel interlocks are evaluated as part of the panelboard, so the kit should be one the panel maker offers or a third-party kit listed for that exact panel model. A kit that fits loosely, or that was cut or drilled to fit, is the kind of thing an inspector turns down. Manual and automatic transfer switches are listed as standalone transfer equipment.
- Inlet warning sign. Article 702 requires a warning near a power inlet that tells you whether the system is wired for a generator with a bonded neutral or a floating neutral. Your generator’s manual says which it is.
- Backfed breaker fastener. The generator breaker must be held in place with a listed retainer (NEC 408.36(D)).
- Matching sizes. The inlet, cable, breaker and cord must all match the generator outlet, 30 amps or 50 amps.
- Labeling. The generator breaker and the switch-over steps should be clearly labeled at the panel.
Code edition and permits in our counties
Harford County adopted the 2023 NEC with county amendments; Baltimore County enforces the 2023 NEC for permits issued after August 31, 2023; Cecil County enforces it for permits from August 2, 2025. In Harford County, electrical permits are applied for at the Permit Center, 220 S. Main Street in Bel Air, by an electrician holding a Harford County license, and a permit is valid for 12 months. The county inspector has the final word on what is accepted. We handle the permit and inspection when the job requires one.
Will an interlock kit fit my panel?
- Panel make and model. The label inside the door tells us. Panels that are no longer made, and some known problem panels, have no listed kit at all. If yours is one of them, a manual transfer switch or a panel replacement is the path.
- Space for the generator breaker. Most interlocks need the generator breaker in the spaces directly beside or below the main. If those spaces hold existing circuits, we move them, which can require a tandem breaker or open space elsewhere.
- Main breaker location. Main-lug panels fed from a separate disconnect outside, which are common where an emergency disconnect has been added at the meter, need a different approach.
- Panel condition. Scorched bus bars, loose breakers or a full panel are worth fixing before adding a generator, because the generator will lean on the same parts.
What we check on site
The panel label and listing, the main breaker rating, open spaces at the top of the bus, the condition of the bus and existing breakers, the generator's outlet and neutral setup, and the shortest sound route from the inlet location to the panel.
How do you switch over to generator power safely?
1
Set the generator outside
2
Connect the cord
3
Turn off the main
4
Turn on the generator breaker
5
Add loads one by one
6
Switch back when power returns
Which should you choose for your home?
Both start with the same inlet and cord, sized to your generator. If you are still choosing a generator, the size you need comes from your must-run loads; our guide on sizing a portable generator shows the math. For the full scope of what we install and how a visit goes, see our generator inlet, interlock and transfer switch installation page. We do this work across Harford, eastern Baltimore and western Cecil counties, including many homes around Bel Air.
To start, text a short video of your open panel door and label, the outside wall near the panel, and your generator’s outlet panel to 410-808-4215. Please Note: Quotes provided from videos are estimates based on the information shown. If additional issues, repairs, materials, or site conditions are discovered that were not visible in the video, the final cost may vary. A more detailed video helps ensure the most accurate quote.
Related reading
FAQ
Questions homeowners ask
Are generator interlock kits legal in Maryland?
Can I install an interlock kit myself?
Does a transfer switch protect lineworkers better than an interlock?
What size generator breaker and inlet do I need?
Can I add a whole-house surge protector at the same time?
Sources
- Harford County Government: Permits (electrical permits and homeowner permits)
- OSHA: Using portable generators safely (fact sheet)
- Generac Support: Why you should never back-feed your electric panel with a generator
- CPSC: Winter storm may knock out power; CPSC warns of deadly carbon monoxide and fire risks (Feb. 2026)