What is a heavy-up? Maryland’s term for an electrical service upgrade

If an electrician or HVAC contractor told you that you need a heavy-up, this is what they mean, what gets replaced, who does which part, and what the day itself looks like.
New meter base and service mast after a heavy-up on a Maryland split-level home

On this page

Short answer · 11 min read

A heavy-up is the utility-coordinated upgrade of your home’s electrical service to a higher amperage, usually from 100 amps to 200 amps. The electrician replaces the service entrance cable or mast, the meter base, the main panel and the grounding, under a permit. The utility disconnects power, and after inspection it reconnects and sets the meter.

Key takeaways

Heavy-up is one of those words you hear in Maryland and almost nowhere else. An HVAC company quoting a heat pump writes “heavy-up by others” on the proposal, or an EV dealer says your house will need one. This post, part of our electrical panel guide, explains the term in plain language.

A heavy-up is the utility-coordinated upgrade of your service entrance, meter base and panel to a higher amperage, usually 100A to 200A. It is bigger than a panel swap because it changes how much power the utility can deliver to your house, so it involves a permit, a county inspection and the utility’s crew. Below: what gets replaced, how coordination with BGE or Delmarva Power works, what the day looks like, and how to tell whether you need one at all.

What does heavy-up mean in electrical work?

In electrical work, a heavy-up means increasing a building’s electrical service to a higher amp rating, with the utility disconnecting and reconnecting power. The word is regional shorthand used around Maryland, Washington, DC and Northern Virginia. Utilities and the National Electrical Code call the same job a service upgrade or service change.

The term covers more than one starting point. In older Baltimore County rowhomes and Havre de Grace houses, a heavy-up may take a 60 amp fuse service to 200 amps. In 1960s to 1980s ranchers and split-levels across Harford County, it is usually 100A to 200A. In large all-electric homes, it can mean going from 200 amps to a 320 or 400 amp class service, which needs more utility engineering.

What makes it a heavy-up, rather than a panel replacement, is the service. A 200 amp panel fed by 100 amp service cable and a 100 amp meter base is still a 100 amp house. A heavy-up replaces every part of the path that limits the current, so the whole service carries the new rating.

What gets replaced in a heavy-up?

A heavy-up replaces the service entrance cable or mast, the meter base, the main panel or main disconnect, and usually the grounding and bonding. The utility handles its own equipment on the other side of the meter. Here is who owns what on a typical overhead service.

Who owns and replaces each part of a residential service

ComponentWho owns itChanged in a heavy-up?
Service drop (overhead wires from the pole)UtilityThe utility decides if it needs upgrading
Weatherhead, mast or service entrance cableHomeownerYes, sized for the new rating
Meter base (the socket the meter plugs into)HomeownerYes, usually replaced
Electric meterUtilityUtility removes and resets it
Main panel or main disconnectHomeownerYes, new 200A equipment
Grounding electrodes and bondingHomeownerBrought up to current code
Surge protective device at the serviceHomeownerAdded where the code requires it
Current code adds a few items that older services never had. The 2023 NEC requires surge protection for dwelling services under 230.67, including when service equipment is replaced. It also requires an outdoor emergency disconnect for one- and two-family homes under 230.85. Counties can amend these sections, so the county inspector has the final word on how they apply in your jurisdiction.

Grounding is the part people forget. Older homes often have a single ground rod or rely on a water pipe connection that was cut when plumbing was replaced with plastic. A heavy-up is when the grounding electrode system gets checked and corrected, because the new panel is only as safe as its path to ground.
New 200 amp meter base and service cable on a brick rancher in Maryland
A new 200 amp meter base and service cable on a brick rancher after a heavy-up. The utility owns and sets the meter itself.

How does BGE coordination work on a heavy-up?

BGE coordination works through a service request: the electrician or homeowner tells BGE what service size is needed, BGE schedules the disconnect, and BGE reconnects after the county approves the work. For a residential service increase of 200 amps or less, BGE lets customers submit a no-design service request through its Service Installation and Upgrades Portal. Bigger services go through design and engineering, which takes longer.

1

Confirm the need

A load calculation shows the house needs more capacity, or the existing service equipment is worn out. We also confirm your utility from your bill, because northern Harford and Cecil County addresses may be Delmarva Power.

2

Pull the permit

We apply for the electrical permit with the county: the Harford County Permit Center in Bel Air, Baltimore County Permits, Approvals and Inspections in Towson, or Cecil County Permits and Inspections in Elkton.

3

Submit the utility request

The service request tells the utility the new main disconnect size and load. BGE’s own guidance says that if you don’t know your load requirements, you need to consult an electrician.

4

Schedule the outage

The utility disconnects the service at the meter or the pole. We schedule the work day around that window.

5

Install and inspect

We replace the service equipment, panel and grounding. A county inspector, or in Cecil County a third-party inspection agency, checks the work.

6

Reconnect and set the meter

After approval, the utility reconnects the service and sets the meter. Power comes back on through the new panel, and we verify every circuit.

Maryland utility and permit notes

Most Harford and all Baltimore County homes in our area are BGE customers. Cecil County and a small northern slice of Harford are Delmarva Power, which has its own request process. Baltimore County requires a permit for nearly all electrical work, pulled by a county-registered licensed electrical contractor. Cecil County enforces the 2023 NEC for permits from August 2, 2025, with inspections by authorized third-party agencies. We handle the permit and inspection when the job requires one.

Wondering what your panel can handle?

Text a photo or short video to 410-808-4215 and we’ll reply within 24 hours with what we see and what it means. Burning smell, sparks or a hot panel? Call now, day or night.

How long is the power off during a heavy-up?

On a straightforward 100A to 200A heavy-up, the house is usually without power for one working day. The exact length depends on whether the utility can reconnect the same day the inspection passes, and on how much of the service has to be rebuilt.

Overhead services with a mast that needs replacing take longer than a simple meter base swap. Underground services can add time if the lateral or conduit needs work. If the panel is being moved to a new location, the branch circuits have to be extended to reach it, which adds hours. We tell you the expected window before the day, so you can plan around it.

A few things are worth planning for on heavy-up day:
  • Refrigerator and freezer: keep the doors closed. A full freezer holds temperature far longer than a half-empty one.
  • Sump pump: in a wet season, ask about a temporary plan. This matters in waterfront areas and in basements that take water after storms.
  • Well pump: rural homes in northern Harford and Baltimore County lose water pressure while the power is off. Fill a few containers the night before.
  • Medical equipment: tell us in advance about any powered medical device so we can plan the schedule around it.
  • Work-from-home and security systems: internet, alarms and cameras go down with everything else unless they have battery backup.

Heavy-up, panel replacement or new circuits: which do you need?

You need a heavy-up when the whole service is too small or worn out. You need a panel replacement when the panel is the problem but the service size is fine. You need new circuits when the house has capacity but no circuit in the right place. Getting this right is the difference between a one-day job and a much smaller one.

Three different jobs that often get called the same thing

JobWhat changesUtility involved?
Heavy-up (service upgrade)Service cable or mast, meter base, panel, grounding, all at a higher ratingYes, disconnect and reconnect
Panel replacementPanel and breakers at the same amperageUsually, to remove the meter safely, but no service size change
SubpanelA second panel fed from the main for more spacesNo
New dedicated circuitOne breaker and one run of wireNo
If you are not sure which bucket you are in, our post on the signs you need a panel upgrade sorts the symptoms. For the capacity question itself, see 100 amp vs 200 amp service, which covers which homes need which and why.

Do overhead and underground services change the heavy-up?

Yes. Overhead services usually mean replacing the mast or service entrance cable up to the weatherhead, while underground services mean working with the conduit and conductors that come up into the meter base from below. The type of service you have shapes how much of the job is outside the house and how much coordination the utility needs.

Overhead service

Many split-levels and ranchers in Harford County have an overhead drop from a pole to a weatherhead on the roof or the side of the house. The mast must be strong enough to hold the drop and tall enough to keep the wires at the clearances the code and the utility require over roofs, driveways and walkways. A heavy-up often replaces the mast, the weatherhead and the cable down to a new meter base. A leaning mast or cracked cable jacket is a reason to do this even without a capacity problem.
Overhead service mast, weatherhead and meter base on the side of a split-level home in Maryland.
An overhead service mast and weatherhead on a split-level home. On many heavy-ups the mast and cable are replaced along with the meter base.

Underground service

Newer subdivisions, like many 1990s and later neighborhoods around Bel Air South and Forest Hill, often have underground service. The lateral runs underground to the meter base. Whether the existing underground conductors can carry 200 amps, and who replaces them if not, depends on the utility and the installation. We confirm that before quoting, because trenching or new conduit changes the scope.

How do you know if you need a heavy-up?

You likely need a heavy-up if your main breaker trips, if a load calculation shows the service is too small for new equipment, or if your meter base and service cable are worn out. A contractor’s note on a heat pump or EV proposal is a good prompt to check, but it is not the same as a calculation.

The most common triggers in our area are a planned EV charger, a switch from oil or propane heat to a heat pump, a hot tub, a kitchen remodel with an induction range, or a finished basement or addition. Older 60 amp fuse services in places like Dundalk and older Towson neighborhoods almost always need a heavy-up before any of those loads are added.

Our 200 amp service upgrade page covers the work we do and how we handle BGE and Delmarva Power scheduling. If you want to understand the price before you call, our post on panel upgrade cost in Maryland explains the factors that move it. To start, call or text 410-808-4215.

Do not touch the meter or service cable

The service cable and meter base are energized even with your main breaker off, because they sit on the utility side of it. Never pull a meter, cut a seal or work on the service yourself. If a storm has pulled the drop off the house or the mast is bent, stay clear and call BGE or Delmarva Power first, then us.

Related reading

Which homes need which, with the math behind EVs, heat pumps and electric appliances.
Capacity signs, condition signs, and the few that mean call today.
How electricians decide whether your service has room for a new load.

FAQ

Questions homeowners ask

Not quite. A panel upgrade can mean replacing the panel at the same amperage, with no change to how much power the utility can deliver. A heavy-up raises the service rating, so it replaces the meter base and service conductors too, and the utility has to be involved. People often use the terms loosely, so ask your electrician which parts are being replaced and what the new service rating will be.
Charges for utility-side work depend on BGE’s tariff and the specific job, and BGE assesses them during its review of the request. Many residential increases to 200 amps go through BGE’s no-design service request, but if the transformer or service drop needs work, the scope can change. We confirm the utility’s requirements during the request process, so there are no surprises on the work day.
Yes. Most homeowners stay home, and it helps to have someone there to answer questions about circuits. The house will be without power for most of the day, so plan for no heat or air conditioning, no well water, and no internet. Keep pets away from the work area outside and away from the panel location inside, and keep driveway access clear for the utility truck.
No. A heavy-up replaces the service equipment and panel, and the existing branch circuits are reconnected to the new panel. Some circuits may need new breakers or short extensions if the panel moves, and damaged or unsafe wiring found during the job will be pointed out. Older wiring such as aluminum branch circuits or knob-and-tube is a separate question that the electrician should discuss with you.
Start as soon as you know a big load is coming, such as an EV delivery date or a heat pump install. The permit, the utility request and the scheduling of the disconnect all take time, and the utility’s schedule usually sets the pace. Getting the load calculation and permit done early keeps the heat pump or charger installer from waiting on the service.
Michael Cliffe, owner of Snapper Electric

Reviewed for accuracy

Michael Cliffe, Owner · Maryland State Licensed Contractor, License 7788

Written by the Snapper Electric team · Last updated October 25, 2026

Electrical work can be dangerous. The information on this page is general guidance for homeowners in Maryland and is not a substitute for an on-site assessment by a licensed electrician. Always turn off power at the breaker before touching any wiring, and call 911 if you smell burning, see sparks, or have an active electrical fire.

Keep reading

More guides like this

Ready when you are.

Call, text, or send the form. We’ll tell you what we see, what it means for your home, and what it costs before any work starts.
Office hours Mon–Sat 8 AM–5 PM · 24/7 for electrical emergencies
Snapper Electric turtle mascot